I agree, that A,B,C are wrong. I’ve just spotted the “C” errors.
They all give an incorrect award period length for the calcs.
I’ve been trying to use the case studies to test a new version of my quickcalc tool. Makes it a bit difficult.
How have all these errors got through?
Another error is in Case study B – just underneath the working out for the CTC award of £115.35 pw it says
“£39.20 is the amount you should take into account……”
That’s the amount from case study A!
I think these people need about 20 visits from the auditors.