Reply To: Reconsiderations

#9210
markp
Participant

I assume that you notified of the termination no earlier than 25.7.06.

As I see it………..

The date of the request for the reconsideration has to be 25.8.06 but, assuming you are revising the original decision, you would be setting aside the defective decision ( to which I assume your temination refers) and issuing a revised decision which would be effective from 30.6.06 and your info received date would be the date you received the information to enable the revision.

Assuming that you weren’t going to revise the original decision the dayte of the request for reconsideration has to be 25.8.06.

Waiting, as ever, to be corrected!………………

Do I know what I'm doing? The jury's out on that........................