End of I.S./JSA etc & EPP period (Northgate Users)

Currently, there are 0 users and 1 guest visiting this topic.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #31737
    liffe
    Participant

    Can I ask how other Northgate users process an end of entitlement to i.s. etc & then an EPP award. We terminate the benefit period & award the EPP for 4 weeks as a separate period & treat them as 2 separate change in circs. How does anybody else do this?

    #88785
    darren_w
    Participant

    We terminate the benefit period but take the C/C tick out, then process an EPP period with the C/C tick in so that the two calculations are only counted as one change. If benefit entitlement is continuous we then process another CONT period (C/C tick in) to reflect this change.

    #88786
    Anonymous
    Guest

    We do the same as darren_w !!

    #88787
    liffe
    Participant

    Thank you both

Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.